ON FACADES manages the installation of Cold-formed Steel Framing from site
survey and design coordination through to erection, inspection and handover. We
install site-assembled frames or preassembled panels to suit the approved
system and erection sequence.
We’ll
organise our installation sequences of SFS in two main categories relating to
the most used applications in construction buildings:
Freestanding
SFS
Freestanding
SFS is used for elements such as parapets, downstands, screens and independent
walls. It carries its own weight, wind loads and any specified finishes. It
relies on its designed base connections and, where specified, returns, ties or
bracing for stability.
Load-bearing
SFS
Load-bearing SFS forms part of
the building’s structure. It carries loads from floors, roofs or walls above
and transfers them through the designed bearings and connections to the
supporting structure.
We cover the following related
services:
Pre-Installation
Phase
- Project
Assessment and Site Survey
- Design
Assessment and Coordination
- Safe
Systems of Work, Lifting and temporary stability
- Delivery
Schedule Coordination
Installation
Phase
- Site
Preparation, Setting Out and
support fixings
- Framing
installation sequences relating to their application
- Freestanding
SFS
- Load-bearing
SFS
- Framing
installation sequences relating to their assembly method
- Slab-to-soffit
infill with site-assembled studs and tracks
- Slab-to-soffit
infill with preassembled panels
- Continuous
oversail walling with site-assembled studs and tracks
- Continuous
oversail walling with preassembled panels
- Alignment,
adjustments, testing and inspection releases
- Sheathing,
insulation and fire protection interfaces
Post-Installation
Phase
- Sealing,
waterproofing and finishing
- Cleaning,
detailing and protection
- Quality
assurance, documentation and handover
- Client
briefing and aftercare support
Project
Management and Documentation
Our site managers coordinate
workface releases, installers, deliveries and lifting with the principal
contractor and other trades. They maintain daily records by area, track drawing
revisions and design queries, and record inspection status and changes to the
sequence. The affected team is briefed before work resumes under a revised
detail or method.
Our commitment
We install load-bearing and
freestanding SFS in line with the approved design and erection sequence. Our
site teams check fixings, alignment and frame stability at each agreed
inspection stage. We record those checks and hand over each work area with clear
information on what has been signed off and any restrictions that apply to
follow-on trades.
Technical References
○ voestalpine Metsec What is
SFS?
○ voestalpine Metsec Infill
walling
○ voestalpine Metsec Continuous
walling
○ voestalpine Metsec Metframe load-bearing structures
○ FIS and SCI Light steel
external wall systems installation guidance
○ SCI Light steel
framing installation guidance
○ HSE Steel
erection
○ HSE Temporary
works
ON FACADES manages the installation of Cold-formed Steel Framing from site
survey and design coordination through to erection, inspection and handover. We
install site-assembled frames or preassembled panels to suit the approved
system and erection sequence.
We cover the following related services:
Pre-Installation
Phase
- Project
Assessment and Site Survey
- Review
architectural and structural drawings, elevations, framing and fixing
schedules and panel layouts. Identify where the system is load-bearing,
freestanding, slab-to-soffit infill or continuous walling outboard of the
slab edge.
- Survey
gridlines, slab and soffit levels, slab edges, openings, support faces
and cast-in items. Measure slab-to-soffit heights at the planned stud or
panel positions and check the available bearing surfaces and anchor edge
distances.
- Record
the condition and tolerances of the receiving structure. Flag damaged
concrete, missing embeds, unverified substrates and obstructions. Agree
any remedial works or revised details before releasing the area.
- Review
access to each workface, unloading and decanting areas, lifting routes
and landing positions. Confirm where material packs and plant can be
placed within the approved loading limits.
- Design
Assessment and Coordination
- Confirm
section marks, steel thickness, protective coating, stud centres, tracks,
cleats, anchors, temporary restraint, permanent bracing and structural
sheathing. Check connection orientation, fixing positions, allowable
packing and tolerances.
- Identify
what carries vertical load and what provides lateral restraint at each
junction. Confirm the required clearances, slot travel and movement
direction for infill heads, slab-edge restraints and panel joints. Check
which erection stages need a release before further loading.
- Coordinate
openings, jambs, lintels, sills, parapets and support zones with
cladding, glazing, roofing and services. Agree responsibility for boards,
insulation, membranes, cavity barriers, fire stopping and continuity at
trade interfaces.
- Agree
the first bay or panel, inspection frequencies, test requirements and
signatories in the ITP. Resolve discrepancies through the responsible
designer and issue the revised detail before progressing the affected
work.
- Safe Systems
of Work, Lifting and temporary stability
- Prepare
and brief project RAMS covering work at height, slab edges, lifting and
landing, temporary instability, sharp steel edges, manual handling,
cutting and drilling. Agree collective edge protection, safe access,
exclusion zones, dropped-object controls and rescue arrangements.
- Agree
the erection sequence and temporary works design, including restraint
locations, anchor requirements, stage checks, permissible wind
conditions, safe stopping positions and the authority to release or
remove restraints.
- Where
lifting is required, use the approved lift plan. Confirm actual panel
weight and centre of gravity, including attached boards or insulation,
lifting points, lifting accessories, capacity at working radius, landing
crew, communication and wind limits. Account for the sail area of boarded
panels.
- Delivery
Schedule Coordination
- Schedule
deliveries and distribution by elevation, level, bay or panel mark. Match
delivery racks, handling equipment and floor loading limits to the
intended unloading and storage sequence.
- Check
deliveries against the release schedule for section and panel marks,
orientation, dimensions, components, fixings and damage. Quarantine
incorrect or damaged items and refer suspected distortion or coating
damage for an agreed disposition.
- Store
components supported, secured and protected from standing water. Keep
panel restraints in place until the approved unloading sequence calls for
release. Keep fixings identifiable and consumables within their storage
and shelf-life requirements.
Installation
Phase
- Site
Preparation, Setting Out and support fixings
- Confirm
the workface, access equipment and edge protection have been released for
use. Check the designated loading and laydown areas and keep lifting and
handling routes clear.
- Transfer
datums and mark tracks, panel lines, openings and anchor positions.
Recheck levels and bearing surfaces against the survey and drawings.
Agree how to resolve out-of-tolerance conditions before fixing.
- Check
the approved drilling zones and locate embedded services, reinforcement
and post-tensioning where relevant. Resolve conflicts before drilling or
moving an anchor position.
- Install specified base tracks or sole plates, isolation
layers, packers or grout and base fixings in the approved sequence.
Follow the anchor detail and product instructions for edge distances,
spacing, embedment, hole preparation and tightening or curing
requirements.
- Framing
Installation Sequences relating to their application
·
Freestanding
SFS
- Set out
the wall, screen or parapet and verify the structure receiving its base
and restraint reactions. Check the required base restraint detail,
including any posts, returns, ties or backstays, and allow for adjacent
movement joints.
- Install
the designed base channel, posts or support brackets. Check bearing,
packing and anchorage before erecting framing. Start from the location
shown in the approved erection sequence.
- For
site assembly, fit and restrain the initial post or stud as the sequence
requires, then install the remaining studs, tracks, noggins and cap
members. For preassembled freestanding panels, verify panel marks and
lift points, then place each panel and secure the required connections
and temporary restraints before releasing the lifting gear.
- Add
permanent returns, bracing, ties or backstays as shown. Check each stage
for stability, including before boarding or fitting a facing that
increases wind exposure. Verify parapet heights, coping support and roof
waterproofing interfaces where applicable.
- Check
base fixings, line, plumb and restraints. Leave the frame in its approved
secure condition and keep temporary restraint in place until authorised
removal.
·
Load-Bearing
SFS
- Start
from the approved braced bay or other designated start point. Check the
receiving structure, levels, bearings and hold-down positions. Install
the specified sole plates or base tracks, isolation layers and packing or
grout in the approved order.
- For
site assembly, install studs, tracks and restraint as the frame is
erected. For panel erection, match each panel mark and orientation to the
erection drawing, lift at the designated points, land on the specified
bearings and install the required initial connections and temporary
bracing before releasing the lifting gear.
- Form
openings and junctions with the specified jambs, trimmers, headers,
blocking and ties. Verify the alignment of load-bearing studs or other
bearing members over supports below and check support beneath
concentrated loads.
- Install
permanent bracing, hold-downs, structural sheathing, floor or roof
members, and diaphragm connections as specified for the stage. Check the
sheathing grade, orientation, edge support and fixing pattern where it
contributes to stability.
- Inspect and record bearings, connections and the
required stability system. Release each stage in line with the ITP before
landing floor or roof elements, erecting the next level or applying
construction loads. Remove temporary restraint only after the designated
person authorises removal.
- Framing
installation sequences relating to their assembly method
·
Slab-to-soffit
infill with site-assembled studs and tracks
- Set out
the wall line between the slab and the soffit. Fix the specified base
track and head track and check alignment. Where a deflection head is
required, confirm the correct track, clearance and connection detail for
the measured opening.
- Confirm
stud marks, actual lengths and centres. Fit studs to the base and head
detail in the specified orientation. Form corners, openings and jamb,
lintel and sill details and fit specified noggins and reinforcement.
- Fix
studs to the tracks as detailed. Fit the approved slip or slotted
connection where specified. Verify the required head clearance and slot
travel, including at jambs and abutments. Keep the movement zone clear of
rigid fixings, board or finishes that would bridge it.
- Check
frame line, plumb, opening dimensions, fixing pattern and movement
clearance before boarding or handing over the bay.
·
Slab-to-Soffit
Infill with Preassembled Panels
- Match
the panel mark, orientation and dimensions to the bay and confirm the
lifting arrangement. Check the measured opening, head clearance,
receiving tracks or brackets, and access for positioning. Inspect any
factory-fitted boards or membranes before lifting.
- Move
the panel into the opening using the approved handling method. Land it on
the specified base support and install the required base, head and side
connections or temporary restraints before releasing the lifting gear,
where used.
- Align
the panel, set the joints and fit the specified panel-to-panel and
perimeter connections. Check that the head connection accommodates the
design movement and that any joint fixings allow the intended relative
movement.
- Inspect
concealed connections before closing the joint, including access behind
pre-fitted boards where applicable. Check panel line, opening geometry,
clearances and joint interfaces before proceeding.
·
Continuous
Oversail Walling with Site-Assembled Studs and Tracks
- Set out
the external face, offsets, start level and restraint positions at each
slab edge. Install the designed base support or dead-load brackets and
the intermediate slab-edge cleats or restraints in the approved order.
Identify on the workface which connections carry weight and which allow
movement.
- Erect
the first stud or group of studs over the slab edge from the designated
protected work position. Set to line and fix to the specified load
support and lateral restraints. Secure each erection stage as detailed
before releasing handling equipment or progressing.
- Continue
with the specified stud lengths and section orientation. Form splices,
capping or inter-storey tracks, corners, openings and movement joints
only at the positions shown. Check bearing and continuity before erecting
the next lift of studs.
- Set
movement connections to the designed position and check slot direction
and available travel. Check the facade plane across levels, and verify
bracket fixings, splices and movement zones before boarding.
·
Continuous
Oversail Walling with Preassembled Panels
- Set out
panel joints and bracket positions on each level. Confirm panel marks,
size, orientation, weight, fixing access and installation order. Install
and survey the designed weight-bearing supports and lateral or movement
restraints.
- Lift
each panel to the exterior face using the approved lift plan. Land it on
or connect it to the designated supports and fit the required restraint
and temporary bracing before releasing lifting gear. Confirm the first
panel is stable before bringing the next into position.
- Adjust
panel line, level, plumb and joint widths within the permitted
adjustment. Fit inter-panel ties, splices and closures as detailed.
Verify that weight is carried at the designated points and that the other
connections provide the intended lateral restraint and movement.
- Inspect
support brackets, anchor fixings and panel connections from the agreed
access points. Check joint movement and continuity of any factory-fitted
boards or weather layers before closure. Record the release of each bay
or lift before installing the next stage.
- Alignment,
Adjustments and Testing
- Check
datum, line, level, plumb, stud centres, panel joints and opening
dimensions. Record measured values against the drawing tolerances and
raise any deviation before concealment.
- Check
member marks, anchors, connection fixings, bearings, bracing and
restraint. Record installation details and results of proof or pull-out
testing where specified, using the agreed test locations, method and
acceptance criteria.
- Check
movement gaps and slotted connections after adjoining work that could
restrict movement. Confirm each erection stage is stable before pausing
work and arrange reinspection before restarting if wind, impact or
another event could have affected the frame.
- Record
separate releases where required before further loading, temporary
restraint removal and closing up. Photograph items that will be concealed
and complete the applicable ITP sign-offs.
- Sheathing,
Insulation and Fire Protection Interfaces
- Fit
structural or external sheathing within the agreed scope and sequence.
Confirm type, orientation, joints, supports and fixing pattern. Where
sheathing provides stability, install and inspect it at the erection
stage required by the design.
- Install
insulation, membranes, cavity barriers and fire stopping where included,
to the approved assembly details. Check continuity and fixings at panel
joints, slab edges, openings, penetrations and parapets. Obtain the
required inspections before covering each layer.