A comprehensive installation plan for Louvre, Brise Soleil, Soffit
and Coping Systems ensures that every phase from pre-installation
planning through to client handover is executed with precision. By
incorporating detailed site surveys, rigorous design assessments, and
structured installation and post-installation reviews, the process is designed
to achieve the highest standards in quality, safety, and performance.
We cover the following related services:
Pre-Installation
Phase
 - Project
     Assessment and Site Survey
 
 - Design
     Assessment and Coordination
 
 - Create
     and review the Safe Systems of Works
 
 - Delivery
     Schedule Coordination
 
Installation
Phase
 - Site
     Preparation
 
 - Layout,
     Marking and Pre-installation of Substructures
 
 - Installation
     of Louvre, Brise Soleil, Soffit, Fascia and Coping Systems
 
 - Alignment,
     Adjustments and Testing
 
Post-Installation
Phase
 - Sealing,
     Waterproofing and Finishing
 
 - Cleaning,
     Detailing and Protection
 
 - Quality
     Assurance, Documentation and Handover
 
 - Client
     Training and Aftercare Support
 
Project
Management and Documentation
Throughout the installation process, our?site teams maintain
detailed documentation of all activities, including daily logs, inspection
reports, and communication records. Our Site Managers will use adequate project
management forms to track progress, and manage resources, to ensure timely
completion of the project.
Our commitment
Adhering to our methodology
for the installation of Louvre, Brise Soleil, Soffit, and Coping Systems not
only meets industry requirements but also supports the long-term durability and
aesthetic integrity of the building envelope. This approach, modelled after the
stringent standards outlined in our trade?s code of practice, ensures that
every critical element is comprehensively addressed, paving the way for a
successful and enduring project delivery.
                                                          
 
                      A comprehensive installation
plan for Louvre, Brise Soleil, Soffit and Coping Systems ensures
that every phase from pre-installation planning through to client handover is
executed with precision. By incorporating detailed site surveys, rigorous
design assessments, and structured installation and post-installation reviews,
the process is designed to achieve the highest standards in quality, safety,
and performance.
We cover the following related services:
Pre-Installation
Phase
 - Project
     Assessment and Site Survey
 
 
  - Examine
      architectural, structural, and detail drawings; specifications; and
      design intent for Louvre, Brise Soleil, Soffit, and Coping systems.
 
  - Conduct
      a detailed site survey to verify dimensions, substrate conditions and
      environmental factors that might affect installation (e.g., building
      curvature, wind loads, and potential obstructions).
 
  - Evaluate
      potential interferences with adjacent systems, such as cladding or
      waterproofing layers.
 
  - Perform
      a site visit to review accessibility to workfaces and logistic
      requirements for the unloading, decanting and distribution of materials.
 
 
 - Design
     Assessment and Coordination
 
 
  - Review
      the installation drawings and collaborate with designers and engineers to
      validate the proposed design, ensuring the hidden or impossible fixings
      are eliminated and establishing the most efficient installation sequence.
 
  - Verify
      compatibility between the Louvre and Brise Soleil systems, ensuring that
      their operational functions (like adjustable louvres or shading panels)
      work in harmony with the soffit and coping detailing.
 
  - Ensure
      that the soffit and coping systems integrate seamlessly with adjacent
      cladding or roof assemblies, identifying any additional reinforcements or
      weatherproofing solutions required.
 
 
 - Create
     and review the Safe Systems of Works
 
 
  - Develop
      and review comprehensive risk assessments (RAMS) that address the unique
      challenges of handling and installing large, pre-fabricated units,
      working at heights, and near heavy plant or pedestrian traffic.
 
  - Establish
      emergency procedures and ensure that all crew members are trained and
      briefed on best practices for handling and installing the systems.
 
  - Prepare
      detailed lifting plans considering the weight distribution and fragility
      of materials, using appropriate lifting gear to minimise potential
      damage.
 
 
 - Delivery
     Schedule Coordination
 
 
  - Schedule
      deliveries in line with the installation sequence, ensuring storage areas
      are secure and environmentally controlled where necessary.
 
  - Perform
      quality inspections on delivery to check for any damage or deviations
      from specified tolerances.
 
 
Installation
Phase
 - Site
     Preparation
 
 
  - Resource
      the storage needs for tools and sensible materials, lifting equipment and
      accessories, access requirements, PPE, consumables, safety barriers and
      man-safe systems, and any other necessary equipment.
 
  - Designate
      weather-protected storage areas for the Louvre, Brise Soleil, soffit, and
      coping components to prevent damage and ease transportation.
 
  - Ensure
      that installation zones are clearly demarcated with safety barriers and
      that all access points for crane or lift operations are established and
      secure.
 
  - Set
      up temporary safety nets, guardrails, and signage in the work areas,
      especially on elevated or hard-to-reach parts of the building envelope.
 
  - Ensure
      all installation personnel are equipped with the required personal
      protective equipment (PPE), have the appropriate training and have been
      briefed on all required emergency and rescue procedures.
 
 
 - Layout,
     Marking and Pre-installation of substructures
 
 
  - Use
      laser levels, plumb lines, and other precision tools to mark the
      positions for louvre and shading elements, soffit supports, and coping
      fixings, ensuring the layout conforms to design drawings.
 
  - Account
      for expansion joints, tolerances, and aesthetic alignments across
      different building segments.
 
  - Where
      required, install brackets, framing elements, or support rails that will
      serve as the primary attachment points for the Louvre, Brise Soleil and Coping
      systems.
 
 
 - Installation
     of Louvre, Brise Soleil, Soffit, Fascia and Coping Systems
 
 Louvre and
Brise Soleil Systems:
 
  - Secure
      louvre or shading panels to their sub-frames using designated fasteners
      and alignment tools.
 
  - For
      systems with operable elements, install mechanical or automated control
      systems and verify that louvre movements are smooth and unrestricted.
 
  - Confirm
      that the panels are plumb, level, and uniformly spaced.
 
  - Apply
      interim sealants if required to maintain immediate weather protection
      during installation.
 
 
 Soffit,
Fascia and Coping Systems:
 
  - Install
      the cladding elements with care to maintain the integrity of the
      waterproofing system.
 
  - Secure
      soffit elements (whether composite, metal, or other materials) with
      accurate fastenings at the right spacing and level to align with the
      overall facade envelope.
 
  - Use
      proper anchoring techniques to cope with thermal expansions and building
      movement.
 
  - Ensure
      ventilation requirements are met if the soffit incorporates airflow or
      drainage components.
 
  - Ensure
      the fire barrier routes are followed and installed as per the building's
      approved fire safety design.
 
  - Seal the
      fire barrier slabs at their connection with the substructure, at joints and
      the OSCI insulation on the back of the panels with silver tape to ensure the
      complete functionality and integrity of the fireproofing system.
 
  - Ensure
      the air gaps from the horizontal fire barriers to the cladding panels are
      kept to their designed size to ensure the functionality of the fire
      expansion elements for the ventilated cladding systems.
 
  - Install
      the insulation system as required, ensuring gaps are kept to a minimum
      around protruding elements and adhering to the building thermal
      specifications for each location.
 
  - Install
      coping components as per design specifications and the right sequencing,
      ensuring that the connection elements (but-straps) are properly sealed to
      protect against water ingress.
 
  - Fit
      end caps and finishers that complement both the aesthetic and functional
      aspects of the building's perimeter.
 
 
 - Alignment,
     Adjustments and Testing
 
 
  - Verify
      that all installed components are true to the design in terms of
      alignment, level, and spacing, making adjustments as necessary to correct
      any deviations.
 
  - For
      adjustable Louvre or Brise Soleil elements, conduct operational tests to
      ensure that mechanisms, drive systems, or manual operations are working
      reliably and smoothly.
 
 
Post-Installation
Phase
 - Sealing,
     Waterproofing, and Finishing
 
 
  - Apply
      the specified sealants and flashing details along joints and edges to
      ensure weatherproofing for both soffit and coping assemblies.
 
  - Check
      all interfaces between systems (e.g., where the coping meets the cladding
      or roof edge) to eliminate potential water ingress.
 
 
 - Cleaning, Detailing and
     Protection
 
 
 
  - Clean
      all surfaces to remove installation debris, smudges, and marks using
      non-abrasive agents suited for the materials installed.
 
  - Inspect
      the edge details, joints, and trim elements to ensure a consistent,
      high-quality finish across the installed systems.
 
  - Apply
      any necessary finishes or protective coatings.
 
 
 - Quality
     Assurance, Documentation and Handover
 
 
  - Carry
      out a comprehensive inspection against design and performance standards,
      verifying correct fixings, alignment, seal integrity, and overall finish
      quality.
 
  - Document
      any discrepancies or issues and address these prior to the final
      handover.
 
  - Prepare
      comprehensive documentation, including as-built drawings, quality test
      reports, maintenance guidelines, and warranty information.
 
 
 - Client Training and
     Aftercare Support
 
 
  - Provide
      the client's maintenance team with operational training on moving
      components (if applicable), routine cleaning, and inspection practices
      specific to each installed system.
 
  - Establish
      clear channels for aftercare support, including scheduled maintenance
      visits and prompt response plans for any issues related to the installed
      systems.
 
 
Project
Management and Documentation
Throughout the installation process, our site teams maintain
detailed documentation of all activities, including daily logs, inspection
reports, and communication records. Our Site Managers will use adequate project
management forms to track progress, and manage resources, to ensure the timely
completion of the project.
Our commitment
Adhering to our methodology
for the installation of Louvre, Brise Soleil, Soffit, and Coping Systems not
only meets industry requirements but also supports the long-term durability and
aesthetic integrity of the building envelope. This approach, modelled after the
stringent standards outlined in our trade's code of practice, ensures that
every critical element is comprehensively addressed, paving the way for a
successful and enduring project delivery